Sample takeoff
This is what comes back.
One sheet from an example project: Office fit-out, Al Olaya, Riyadh. Hover a line to find it on the drawing, or click it to see where the quantity comes from, room by room.
| Ref | Description | Unit | Qty |
|---|---|---|---|
| Ceilings | |||
| C-01 | m² | 83.00 | |
| C-02 | m² | 66.00 | |
| C-03 | m² | 32.50 | |
| Partitions | |||
| P-01 | m² | 126.15 | |
| P-02 | m | 11.00 | |
| Doors | |||
| D-01 | nos | 5 | |
| D-02 | nos | 1 | |
| D-03 | nos | 1 | |
| Lighting | |||
| E-01 | nos | 18 | |
| E-02 | nos | 22 | |
| E-03 | nos | 2 | |
Measurement notes
How this sheet was measured. Every job comes with these.
- 01Areas and lengths measured to wall centrelines.
- 02Partition height taken as 3.0 m, finished floor to underside of slab (section A-301).
- 03Door openings deducted from partition areas. Openings without doors are not measured.
- 04Ceiling areas are not reduced for light fittings, diffusers or access panels.
- 05Store has an exposed soffit and no ceiling is measured.
Queries for you
What the drawings didn't answer, and what we assumed meanwhile.
- Q1Pantry ceiling type is not on the finish schedule. Measured as moisture-resistant gypsum to match the WC. Please confirm.
- Q2Glass partition head detail is missing. Measured full height to 3.0 m.
Have drawings ready?
Upload them now. We check every sheet and confirm the scope and delivery time within 2 working hours, before any work starts.